Synthetic worked example: cost, certification and cash are different

Wholly invented project records showing how to reconcile cost incurred, submitted value, gross and net certification, and cash received.

SYNTHETIC WORKED EXAMPLE. All project records and amounts are wholly invented. This is not a customer case, measured product result, entitlement assessment or legal advice.

Define the snapshot

Practice Project B is wholly invented. The snapshot date is 30 September 2026. All figures are cumulative at that date and use illustrative currency units. For this exercise, cost means recorded cost incurred; submitted value means the amount included in an application; gross certified value means the amount treated as approved in our invented register before retention; cash means amounts actually received.

Assume a 5% retention for arithmetic teaching only. Ignore tax, advance recovery, other deductions, financing costs and disputed contractual terms. Real projects require the actual agreement, authorised records and appropriate professional review.

Invented project cumulative snapshot at 30 September 2026
Measure in this exampleIllustrative currency units
Cost incurred125,000.00
Cumulative submitted value140,000.00
Cumulative gross certified value118,000.00
Illustrative cumulative retention: 5%5,900.00
Cumulative net certified value112,100.00
Cash received to date90,000.00

Reconcile the submission to the invented certification register

The submitted value of 140,000.00 exceeds the invented gross certified value of 118,000.00 by 22,000.00. Assign 16,000.00 to items awaiting supporting evidence and 6,000.00 to a measurement adjustment in this invented register.

This classification is a teaching assumption, not a finding about entitlement. Pending evidence does not guarantee later approval, and a measurement adjustment cannot be resolved without the actual source records.

140,000.00 − 118,000.00 = 22,000.00 = 16,000.00 + 6,000.00

Separate gross certification, net certification and this period

Cumulative retention is 118,000.00 × 5% = 5,900.00. Cumulative net certified value is 112,100.00. Assume the previous cumulative gross certificate was 80,000.00, with retention of 4,000.00 and a previous net value of 76,000.00.

The current-period gross movement is 38,000.00. The retention movement is 1,900.00, so the net movement is 36,100.00. The current-period movement must not be added to the cumulative total again.

(118,000.00 − 80,000.00) − (5,900.00 − 4,000.00) = 36,100.00

Name the gap you are calculating

There is no single interchangeable “gap”. Write the two measures and the snapshot date beside every difference.

Different comparisons from the same invented snapshot
ComparisonArithmeticWhat it shows here
Cost minus gross certification125,000.00 − 118,000.00 = 7,000.00Difference before retention.
Cost minus net certification125,000.00 − 112,100.00 = 12,900.00Difference after the illustrative retention.
Cost minus cash received125,000.00 − 90,000.00 = 35,000.00Cost-to-receipt comparison at this snapshot.
Net certification minus cash received112,100.00 − 90,000.00 = 22,100.00Amount not yet received in the invented register.

Review sources before deciding what to do

For a real review, reconcile the cost ledger, submission, certificate register, retention record and receipts to a common date and currency. Track source versions, reversals and corrections. Assign unresolved items to a human reviewer instead of interpreting every difference as an error, claim or overdue debt.

The calculations do not establish profit, recoverability, entitlement, payment deadlines or delay responsibility. They also do not represent a CAIS service run. A document tool can support a review workflow; it cannot create evidence that is absent from the project record.

Methodology and limits

All inputs were invented for this original example. The method is direct reconciliation and subtraction, with the retention assumption stated explicitly. There are no client records, external benchmarks or verified customer outcomes behind the figures.